Project Library 2017-07-26T11:20:14+00:00

Project Library

List of Deliverables

Report Schedule: Component A

Title Description Due
1| Inception report Reporting Tasks from Inception icluding:
Project Management Plan (Eng)
Transport Modelling Plan (Eng)
Consultation Plan (Eng)
Website (Eng, Gr)
Document Review Report (Eng)
3 months after the Project commencement
2| Data Collection Report Report on all data collected, including report on structure and content of Web-based Data Room (Eng) 4 months after the Project commencement
3| Transport Modelling Deliverables Final transport model including a Transport Modelling Report, a copy of the Transport Model files, and shapefiles for all Without-Project Scenarios
Model Manual, providing instructions for basic model activities
9 months after the Project commencement
4| Problem Analysis Report Full description of activities and results obtained (Eng, Gr) 11 months after the Project commencement
5| Measures Selection Report Reporting on the identification, testing and selection of measures (Eng) 16 months after the Project commencement
6| Draft Transport Plan Report Draft of Document demonstrating emerging Strategy and basis for selection (Eng, Gr) 17 months after the Project commencement
7| SEA Notification Documentation for SEA
SEA Report
Appropriate Assessment Report– if required
Draft Strategic Environmental Assessment Report (Eng, Gr)
17 months after the Project commencement
Final Strategic Environmental Assessment Report (Eng, Gr) 20 months after the Project commencement
8| Final Report and Executive Summary Final Report on Transport Plan (Eng, Gr) 21 months after the Project commencement
9| Programming Report Outline of measures to be implemented across defined programming periods (Eng, Gr) 21 months after the Project commencement
10| Action report Summary of activities, decisions, and all outputs (Eng) 22 months after the Project commencement

Report Schedule: Component Β

Title Description Due
1| Scoping report Report on activities to be undertaken within the support to the SPU, based on consultation and discussion with the beneficiary (Eng, Gr) 4 months after the Project commencement
2| Transport Modelling Training Level 1 Course on Transport Modelling: Overview of Transport Models
Level 2 Course on Transport Modelling: Opening and Viewing Transport Models Scenarios
Level 3 Course on Transport Modelling: Testing and Verifying Models
(Eng)
6, 7 and 8 months after the Project commencement
3| Completion Report Completion report Review of activities undertaken through Component B of the Required Services (Eng, Gr) 22 months after the Project commencement